Get your free

Construction Daily Report Template

Use this free Construction Report Template for Excel to manage your projects better.

A construction worksite is a busy place, and everything that happens on one needs to be detailed and recorded daily. These reports need to be thorough and accurate to give a consistent record of all that took place each and every day of the project.

The best way to make sure you log all these activities is by using our free construction daily report template. It has all the fields you’ll need to fill in, with signature lines for the company and client to make sure everyone is in agreement.

What Is a Construction Daily Report?

A construction daily report is filed at the end of the work day to log everything that occurred on the worksite over the course of that workday.

For example, the daily report lists:

  • All the work that was performed
  • Whether that work was completed on schedule or if there were any delays
  • Any safety inspections that occurred and what was reported
  • A list of visitors to the site
  • The weather

The template is then signed at the bottom and dated by both the construction company and the client, so there’s a record of what happened that everyone agrees with.

Why Use a Construction Daily Report Template?

Using this daily report template is important because it communicates the state of the project to all stakeholders and keeps them informed on daily progress. It’s a way to keep the project owner, site manager, subcontractors and investors in the project on the same page.

Because a construction project is made up of many people doing many different jobs, this construction daily report template is an ideal tool to keep everyone working on the most up-to-date information on the project’s progress and current state.

Construction Daily Report Excel template
An excerpt of ProjectManager.com’s Construction Daily Report Template

The daily report is also a record of what was done by who in the project. This tracks work and gives accountability to the crew and foreman. In fact, it protects them from being blamed for mistakes or delays that were not their fault. When a deadline is missed, the reason is outlined on the daily report template and can’t be unfairly blamed on a worker who wasn’t responsible.

Filling out a daily report after a hard day’s work might feel like a tedious and time-consuming job, but it’s crucial for the reasons noted above. Luckily, with this template, the busy work is done for you and all that’s necessary is filling in the blanks. It shouldn’t take more than five minutes at the end of the day.

Who Uses a Construction Daily Report Template?

The daily report template is usually the responsibility of the site manager to fill out, but the daily report is used by almost everyone involved in the project. It’s like a status report that keeps everybody in the loop.

Therefore, the daily report template will get into the hands of everyone from the site manager to the client. The client is obviously invested in the project and wants to know if they’re on schedule, so they’ll look at that specific section of the report.

On the other hand, subcontractors are going to need to know if there’s a need to order more materials or have a larger crew on site to stay on schedule. Managers will also want to see safety inspection reports. If there was an infraction, they’ll have to take actions to get back to code.

How to Use Our Free Construction Daily Report Template

It’s easy to use our daily report template to summarize the activities of the day on your construction site. Since you have to do one each day, this template will save you a lot of time. Just go down the list and fill in the answers to the fields and share it with the rest of the project team.

Job Overview

Here is where you collect the topline information. The name of the project, its address and the type of job is outlined here. The job number and the date of the report will also be noted, with the name of the person who prepared it.

Work

In this section, you’ll list all the work that was done over the course of the day. These templates are customizable so you can add rows depending on how much work was done over the day. Next to the task list is a status, which is pre-filled with options of to do, doing and done. Again, these can be customized to match your preferred nomenclature.

Crew

This list is of the people who were on the jobsite, including subcontractors, but not visitors to the site. They have their own section later on down the form. The first column identifies the type of worker they are, followed by their name and the hours they worked on the job.

Equipment

All the equipment on the job site is listed here. The type of equipment is placed in the first column. This is followed by its status, which is a drop-down menu with the options in use, idle or out of order. Finally, add the amount of hours that piece of equipment was used during the day.

Materials

Any materials, such as wood, drywall, etc., are listed in this section. First, write the time, then add if it was used or not. The last column is an estimate of how much material is left in your inventory.

Delivered

Here you log any deliveries of materials or supplies that came over the day. The first column lists what type of delivery it is, the second column notes the scheduled delivery time and the third column is where you write when the delivery actually arrived.

Delays

It’s rare that a schedule goes without a hitch. When you do experience a delay, this is the section where you’ll explain it. The first defines the type of delay, such as a delivery or work slowdown. The next column will describe that delay and the third column is where you place how much time was lost due to the delay.

Meetings

Meetings happen throughout the project, from daily standups to stakeholder presentations. If there was a meeting held on the jobsite, list the type, the time it happened, who was in attendance and then summarize what it was about and if any action items were decided on.

Safety Inspection

Safety inspections occur regularly or at least once during the life cycle of the project. Here you can note if one happened on the day being recorded. If there was on, there’s a column to note what happened and if there were any incidents.

Visitors

People come on a jobsite often. This section is where you list who, why and what their title is. If there was a city official there to make sure something was being done to code, for example, this is where they would be written about on the daily report template.

Signatures

The last part of the template is the signature. This is where both the company representative and the client representative look over the details of the daily report template and if everyone is in agreement, both sign and date the document. It is then filed and archived with the other project documents.

How ProjectManager.com Helps with Daily Reports

ProjectManager.com is an award-winning project management software that organizes work for greater efficiency. The tool has unlimited file storage, so it can be a central hub for you to upload all your project documentation to make it easy to save and find.

However, the software does much more than that. All your resources can be tracked on the online Gantt chart. All the equipment, materials and personnel you have on your report can be linked to your project plan on our online Gantt chart.

a screenshot of the gantt chart in ProjectManager.com

Create Daily Reports in a Flash

Even better than your daily report template is a robust reporting feature that can create daily status reports that are dynamic documents that can be filtered to show just the data you want to see. They can easily be shared with the project team and stakeholders. Our tool takes your daily report template to the next level.

a screenshot of a status report in ProjectManager.com

Other Templates to Help With Your Construction Projects

The daily report template doesn’t connect with your construction project management tools, but it does a pretty good job on its own of summarizing the activities of the day. If you’re happy with using templates, we have dozens of free project management templates that can help you manage your construction project. Here are a few.

Change Order Form Template

As you fill in your daily report template there will be issues that require changing some aspect of your project, be it in the schedule or budget. The free change order form is used to get approval for anything that will change the scope of your construction project.

Request for Information (RFI) Template

A must for procurement, as you look for vendors and suppliers to contract with. This free template helps you request information on the goods or services you need and makes sure that they fit within the constraints of your plan and budget.

Punch List Template

The free punch list template helps when you walk the final stage of your construction project with the client and go over all the work that’s done. This template collects any minor tweak or missed step that needs to be completed before the client signs off of the job and sends payment.

Related Content

Construction project management is a big field. If you’re looking for some answers on an aspect of managing your next construction project or any project, visit our site. Our web-page is a hub of information for all things project management, with hundreds of blog posts, tutorial videos and guidebooks. And it’s all free. Here are a few construction posts we cherry-picked for you.

ProjectManager.com is a cloud-based tool that helps you better manage your construction projects. Get a handle on planning, monitoring and reporting to keep your project on track. Help your teams collaborate remotely or on the jobsite to work better together. Try ProjectManager.com today for free with this 30-day trial.

Deliver Your Projects
On Time and Under Budget

Start planning your projects.

Start 30-Day Free Trial